Belmar, Lake Como Await Final OK for Stalled Ocean Avenue Outfall Project

After a nearly two-year wait, construction of a $6.2 million federally funded discharge pipeline is expected soon, replacing these temporary pumps that are set up at Lake Como during heavy rains. Credits: Cathy Goetz
The temporary pumps at Lake Como have been a common sight during times of heavy rain, like last week, when the potential of flooding increases and threatens surrounding homes. Credits: Cathy Goetz

BELMAR/LAKE COMO, NJ — With the recent heavy rains, the temporary pumps at Lake Como have been working overtime to prevent the lake from spilling over its banks.

The situation has many residents with homes sitting in this flood-risk area of Belmar and Lake Como asking: Whatever happened to the $6.2 million project to install a discharge piping system into the ocean that will ease their flooding fears?

After a nearly two-year wait, the federally funded project may soon be under way. Since Belmar received the Superstorm Sandy relief aid from the U.S. Department of Housing and Urban Development (HUD) in May 2015, officials have been working through a regulatory maze to gain a multitude of approvals and permits from federal, state and county agencies.

Sign Up for E-News

“We’ve gone through lots of hoops for a large, very important project that comes with 13 different agency approvals,” Belmar Borough Administrator Colleen Connolly said. “We have now cleared all hurdles but one, and we’re hoping to get that approval shortly, and then we can go out to bid.”

That final approval is in the hands of the N.J. Department of Environmental Protection’s Division of Dam Safety and Flood Control, after it was learned the Ocean Avenue outfall is classified as a dam. As the result, the project was required to comply with all dam regulations, including the need to install concrete cradles to secure the gravity-fed pipe. However, this $100,000 new expenditure fell out of the project's scope and necessitated further approvals in order to be added to the existing bond.

With confidence building that Belmar will soon receive the final go-ahead for the flood prevention project, borough officials will “get to work as fast as we can,” Connolly said, referring to putting the construction work out to bid as the first step.

Once a contractor is selected, installation will commence on the 60-inch-diameter outfall pipe from Lake Como, replacing an inadequate narrow pipe that now drains into the ocean and prompts the need for the temporary pumps to be set up and turned on when heavy rains hit.

The project will be staged so that it will not have an impact on vehicle and pedestrian traffic along Ocean Avenue during the busy summer months.  If final approval is received in the next several weeks, borough officials are setting a completion date of early 2018.

The $6.2 million project is funded through a $50 million HUD Community Development Block Grant-Disaster Recovery administered through the state DEP’s Flood Hazard Risk Reduction Program. The grants are awarded to fund projects that reduce storm surge or flood risk in order to prevent flooding conditions that occurred during Superstorm Sandy from happening again.

Although Belmar, Lake Como and Spring Lake border the lake, Belmar was given jurisdiction over the project. During the epic storm, this area was under water for more than a week — a major reason why Belmar was among eight municipalities in the state to receive this second round of Superstorm Sandy HUD funding.

TAP Into Another Town's News:

Sign Up for E-News

Belmar/Lake Como

Belmar and Lake Como

March 19, 2018

Belmar Police Department reported the following arrests occurred in Belmar and Lake Como from February 1, 2018 to February 27, 2018.


Sonya Alfano, 23, of Wall was charged with contempt on an outstanding warrant after her arrest on February 1 on Route 35 by Police Officer Peter Speakman.

Robert Ramos, 31, of Philadelphia was arrested at Belmar Plaza on February 6 by Police Officer ...

Upcoming Events


Thu, March 22, 1:00 PM

Belmar Arts Center, Belmar

The Book Art Show at Belmar Arts Center


Thu, March 22, 7:00 PM


Belmar Zoning Board of Adjustment


Sat, March 24, 9:00 AM

Bar Anticipation, Lake Como

Kilt Run to Benefit the Belmar/Lake Como St.


Sat, March 24, 11:00 AM

Ale House Sports Bar and Grille, Brielle

Ales for Whales II to Benefit the Marine Mammal ...


Sat, March 24, 11:00 AM

Second, Third and Fourth Avenue Beaches

Belmar Easter Egg Hunt


Sat, March 24, 12:00 PM

Jake's Downtown, Belmar

Jake's Downtown Slider Saturdays


Sat, March 24, 1:00 PM

The Stone Pony, Asbury Park

Paint the Pony Purple to Benefit the Epilepsy ...

Fla. Governor Calls for Armed Officer at All Entry Points at Marjory Stoneman Douglas

March 21, 2018

PARKLAND, FL — Gov. Rick Scott requested armed law enforcement personnel be posted to secure "every point of entry" at Marjory Stoneman Douglas High School, in a letter to Broward County Sheriff Scott Israel and Superintendent Robert Runcie. 

"Following the loss of seventeen innocent lives at Marjory Stoneman Douglas High School, our state has been focused on making ...

JCP&L Preparing for Third Nor’easter that Could Impact Region

March 20, 2018

MORRISTOWN, NJ — Jersey Central Power & Light is preparing for the third nor’easter to hit the region in the past two weeks that could produce more than a foot of heavy, wet snow and the potential for wind gusts up to 45 mph in its service areas, beginning early Wednesday, March 21.

JCP&L personnel have implemented storm and staffing plans and are prepared to respond ...