BERKELEY HEIGHTS, NJ - The Township of Berkeley Heights confirmed the following road project schedule:

Rutgers/Hamilton/Princeton Avenues (portion that meets Park Avenue- Topline Construction will begin doing concrete for curbing, ramps, depressed curbs for driveways, etc… week of November 18.

Briarwood East/West, Fay Place, Ridgewood Place – Topline Construction will begin doing concrete for curbing, ramps, depressed curbs for driveways, etc… week of November 18.

Sign Up for Berkeley Heights Newsletter
Our newsletter delivers the local news that you can trust.

Saw Mill & Cornell - Work will be completed by Monday, November 25. 

Lawrence Drive – Complete; underdrains were inserted to improve drainage, and road was repaired. 

Cedar Green, Pine Grove, Scott & Surrounding Roads - Markouts complete; drainage improvements and corresponding road repair to begin after Thanksgiving. 

Some projects will continue into 2020, depending upon weather conditions.