LITTLE FALLS, NJ - The Office of Little Falls Mayor James Damiano has provided construction updates for the week of Oct. 28 to Nov. 1, 2019:​​​​​​

Electric upgrade project – PSE&G’s contractor will continue the electrical upgrade connecting the Totowa substation to the Cedar Grove substation this week, and their anticipated schedule for the week (which is subject to change and is weather dependent) is as follows:

Monday through Friday: Work will continue on Paterson Avenue and Main Street during the day. Traffic will be open in both directions. Work will also be performed on Wilmore Road (between Main Street and Second Ave) where eastbound traffic will be detoured.

Please plan accordingly as you may wish to avoid these areas during the work.