CLIFTON, NJ -  As part of the Routes 3 and 46 project, an NJDOT contractor will be performing a 12-inch main replacement on Valley Road between Robin Hood Road and St. Philips Drive.

This work is scheduled to start today, May 28, 2020 and will take approximately 6-8 weeks to complete. There will be no road closures during this period.

Customers should note that there may be some unavoidable water discoloration and low pressure at any time during the flushing period.

Sign Up for Passaic Valley Newsletter
Our newsletter delivers the local news that you can trust.

Passaic Valley Water Commission (PVWC) assures all customers that the water will be safe for use during this period; however, customers are cautioned to determine if the water is clear before washing clothes (or any other processing) as staining may occur.

Please call Customer Service at 973-340-4300 with any questions or concerns you may have. 

PVWC regrets any inconvenience this may cause its customers.