SPRINGFIELD, NJ - PSE&G starte their paving work on Monday August 14. The starting streets are as follows:

August 14:  Winfield, Edgewood and Adams Terrace
August 15:  Jefferson Terrace, Irwin Street and Remer Avenue
August 16:  Mapes Avenue, Kipling Avenue and Hillside Avenue
August 17:  Mountain Avenue with balance to follow.

PSG&E anticipates being in town for three weeks to complete this work.  They will be knocking on residents doors today to inform them of the work.

Sign Up for E-News

All work is weather permitting.

The schedule was provided by Township Committeewoman Geri Bujnowski.