SUMMIT, NJ - The City of Summit's Department of Community Services Engineering Division has advised residents that construction on Fernwood Road and Ridge Road has begun, and will continue through May 22.

The first phase of this project includes the installation and upgrade of the drainage system, followed by curb installation, sidewalk repairs and then the full milling and paving of the roadway surface. 

During drainage work, the road may be closed to through traffic, and access to driveways may be restricted when pipe is installed. Police will permit on-street parking on adjacent streets out of the construction zone during this project.